Bricks on the third floor and electrical work
We have finished the partition walls on the second floor and are continuing with the third floor. We started with the plumbing and electrical installations on the first floor.
27 November 2025
T1 Construction Progress — July–August 2026
During July and August, construction works continue to progress as planned. We have started installing the ceramic cladding on the building’s facade, as well as the works for the rooftop swimming pool. Inside the apartments, we have begun the installation of the kitchens. We have also completed the ceramic tiling in the lift areas and the finishing works on the building’s staircases.
10 August 2026
Interior finishing
Floor tiling and ceiling installation in all apartments are mostly completed.
1 April 2026

In July 2025, we submitted documents for a construction licence for the construction of Edificio T2

In July 2025, we submitted documents for a construction licence for the construction of Edificio T2.

Comments

Add comment

Bricks on the third floor and electrical work
We have finished the partition walls on the second floor and are continuing with the third floor. We started with the plumbing and electrical installations on the first floor.
27 November 2025
T1 Construction Progress — July–August 2026
During July and August, construction works continue to progress as planned. We have started installing the ceramic cladding on the building’s facade, as well as the works for the rooftop swimming pool. Inside the apartments, we have begun the installation of the kitchens. We have also completed the ceramic tiling in the lift areas and the finishing works on the building’s staircases.
10 August 2026
Interior finishing
Floor tiling and ceiling installation in all apartments are mostly completed.
1 April 2026
Contact
Point your camera at the QR code
qr barcode whatsapp
or follow the link
Continue in Browser
Point your camera at the QR code
qr barcode telegram
or follow the link
Continue in Browser