Bricks on the fourth floor and electrical work
We have finished the partition walls on the fourth floor and are continuing with the atico-floor (last floor). We started with the plumbing and electrical installations on the first floor.
9 December 2025
Bricks on the third floor and electrical work
We have finished the partition walls on the second floor and are continuing with the third floor. We started with the plumbing and electrical installations on the first floor.
27 November 2025
Construction Update
Tile installation in the bathrooms has been completed. We are currently continuing with the walls plastering.
23 February 2026

T1 Construction Progress — July–August 2026

During July and August, construction works continue to progress as planned. We have started installing the ceramic cladding on the building’s facade, as well as the works for the rooftop swimming pool. Inside the apartments, we have begun the installation of the kitchens. We have also completed the ceramic tiling in the lift areas and the finishing works on the building’s staircases.

Photo gallery

Comments

Add comment

Bricks on the fourth floor and electrical work
We have finished the partition walls on the fourth floor and are continuing with the atico-floor (last floor). We started with the plumbing and electrical installations on the first floor.
9 December 2025
Bricks on the third floor and electrical work
We have finished the partition walls on the second floor and are continuing with the third floor. We started with the plumbing and electrical installations on the first floor.
27 November 2025
Construction Update
Tile installation in the bathrooms has been completed. We are currently continuing with the walls plastering.
23 February 2026
Contact
Point your camera at the QR code
qr barcode whatsapp
or follow the link
Continue in Browser
Point your camera at the QR code
qr barcode telegram
or follow the link
Continue in Browser