T1 Construction Progress — July–August 2026
During July and August, construction works continue to progress as planned. We have started installing the ceramic cladding on the building’s facade, as well as the works for the rooftop swimming pool. Inside the apartments, we have begun the installation of the kitchens. We have also completed the ceramic tiling in the lift areas and the finishing works on the building’s staircases.
10 August 2026
Construction progress
Plastering works in stairwells and common areas of the building are in the final stage. In the apartments, wall tiling in bathrooms has been completed, and the installation of suspended ceilings in these areas is nearing completion. In addition, plumbing and sanitary installations in the bathrooms are in the final stage, leaving these areas prepared for the subsequent installation of sanitary fixtures. Terrace flooring works have also been carried out, with final finishing works currently in progress.
1 May 2026
Interior finishing
Floor tiling and ceiling installation in all apartments are mostly completed.
1 April 2026
Construction Update
Tile installation in the bathrooms has been completed. We are currently continuing with the walls plastering.
23 February 2026
Bricks on the fourth floor and electrical work
We have finished the partition walls on the fourth floor and are continuing with the atico-floor (last floor). We started with the plumbing and electrical installations on the first floor.
9 December 2025
Bricks on the third floor and electrical work
We have finished the partition walls on the second floor and are continuing with the third floor. We started with the plumbing and electrical installations on the first floor.
27 November 2025
Bricks on the first floor
We have finished the partition walls on the first floor and are continuing with the second floor.
17 November 2025
We started laying bricks
We have already finished the structure, poured the roof pool and started to lay bricks on the first floor
23 October 2025
T1 Fourth floor completed
The structure of 4th floor is ready! Today we start to construct floor of atico.
29 September 2025
T1 Third floor completed
The structure of 3nd floor is ready! Today we start to construct 4th floor.
12 September 2025
Contact
Point your camera at the QR code
qr barcode whatsapp
or follow the link
Continue in Browser
Point your camera at the QR code
qr barcode telegram
or follow the link
Continue in Browser